How much does it cost to paint the outside of a house?

Dorde Lalic, founder and owner of NLL MåleriDorde Lalic founder and ownerNLL Måleri · 4 min readLinkedIn

Updated

Scaffolding in front of the gable of a red-painted timber house in Lycke.

For 100 m² of timber façade, NLL Måleri’s estimated labour, paint, tape and protection total is 81,250–112,500 SEK including VAT before any applicable ROT. Scaffolding, repairs and extras are excluded. An exact house price requires the façade’s painted area and agreed scope.

A house with 100 m² of living area does not necessarily have 100 m² of façade to paint. Budget from façade sides, material and actual surfaces to treat.

Estimate your project cost

Select the service, scope and customer type. The calculator loads here.

Request a quote

How do you budget for exterior painting?

Calculate labour, painting materials and other project costs separately. This shows both what the calculation includes and what still needs assessing.

The table shows NLL’s prices per m² painted area, including VAT before any applicable ROT.

Price per m² painted area, including VAT before any applicable ROT.
SurfaceLabourPaint, tape and protectionTotal for these items
Timber façade625–875 SEK187.50–250 SEK812.50–1,125 SEK
Rendered façade500–750 SEK187.50–250 SEK687.50–1,000 SEK
Brick façade500–750 SEK187.50–250 SEK687.50–1,000 SEK

These totals are not comprehensive project prices. Add the items your house needs according to the final quote.

Are windows, doors and roofs included?

Façade painting does not automatically include windows, doors or roofs. List these separately if also required. Doing several jobs together does not mean one square-metre rate applies to all.

How is damaged cladding handled?

Cladding replacement needs a separate quantity and price item. Describe damage and distinguish affected patches from areas only needing painting. The guide to replacing or painting cladding helps define your enquiry.

How do you estimate façade area?

Measure each façade side and total the treated areas. Keep notes so the calculation can be checked before quoting.

How are walls and gables calculated?

A rectangular wall is width × height. A triangular gable is base × height ÷ two. For example, a 10-metre-wide, 3-metre-high wall has a gross area of 30 m² before openings.

Should windows and doors be deducted?

Record opening measurements separately and ask NLL to confirm the painted area used in the quote. This avoids different assumptions in your estimate and the contractor’s quantities. Also describe plinths and other parts to remain unpainted.

What does 100 m² of timber façade cost?

Labour and stated painting materials total 81,250–112,500 SEK including VAT before any applicable ROT. The calculation uses exactly 100 m² of treated timber façade.

Worked example: 100 m² timber façade, including VAT before any applicable ROT.
ItemCalculationAmount
Labour100 × 625–875 SEK62,500–87,500 SEK
Paint, tape and protection100 × 187.50–250 SEK18,750–25,000 SEK
Total before ROTLabour + stated materials81,250–112,500 SEK

Scaffolding, repairs and extras are excluded. This is a calculated range, not a quote for an average house or a documented customer project.

What is the equivalent total for render or brick?

For 100 m² of render or brick, labour and the same materials allowance total 68,750–100,000 SEK including VAT before any applicable ROT. This also assumes painting, not new render or façade structural repairs.

What needs resolving before the final price?

Condition, access and exclusions need assessing before a budget becomes a quote. Specifically ask to:

  • Describe included preparation.
  • State how scaffolding or other access is priced.
  • Specify any repairs.
  • State the chosen paint system and treated surfaces.
  • Describe how changes during work are handled.

Clear scope makes quotes comparable without guessing which extras are missing.

How does timing affect planning?

Request a schedule for the house and chosen treatment. This cost guide promises no fixed number of days. For season and planning questions, see the guide to when façades can be painted in Skåne.

How is a possible ROT deduction calculated?

ROT may reduce eligible labour by up to 30% when conditions and allowance permit. See Skatteverket.

For 100 m² of timber façade, labour and stated materials become 62,500–86,250 SEK after a 30% deduction on all labour in the example. Full entitlement is assumed. Other project costs are extra, and materials remain unchanged.

How do you get a price for your house?

Gather measurements, façade material, location and photos of all affected sides. Read about NLL’s exterior wall painting, use the cost calculator for your project and send the details for a quote. Explain which parts of your budget remain estimates.

✎ Get a fixed price
Request a fixed priceEstimate your project cost